Bridge Replacement Project Announced For SE Highland County
Article Presented By Scioto Valley Dumpsters…
(Hillsboro) – Work is set to begin on March 1st for a bridge replacement on Straight Creek Road (T.R. 239) in southeastern Highland County. The project is located approximately 0.5 miles west of State Route 41, and will replace the existing structure over Baker Fork Creek. The roadway will be closed for the duration of the project starting March 6th.
During the closure, traffic will be detoured via S.R. 41, Sinking Spring Road, and Elmville Road.
Cooper’s Excavating, LLC was awarded the construction contract for an estimated cost of $735,000. The project was sponsored by the Highland County Engineer’s Office and ODOT District 9 will be administering the contract.
Estimated completion: Summer 2023