Chillicothe, Ohio (Thursday, April 29, 2021) – The following construction projects are anticipated to affect highways in Ross County next week. All outlined work is weather permitting.

State Route 104 Resurfacing – S.R. 104 will be reduced to one lane daily between Fairgrounds Road and the Pickaway County Line from 7 AM to 5 PM, Mon-Fri starting April 19.Estimated completion: Summer 2021

State Route 28 Resurfacing – S.R. 28 will be reduced to one lane daily from 7 AM to 5 PM between S.R. 138 and Harper Station Road starting April 15. Traffic will be maintained using flaggers. Estimated completion: Summer 2021

Scioto Trails State Park Culvert Replacement – Scioto Trails Forest Road 5 will be closed for 60 days near the intersection with Stony Creek Road starting March 22. Estimated completion: Spring 2021

Tar Hollow State Park Slide Repair – Park Road 10 will be closed for 30 days in Tar Hollow State Park for a slide repair project starting March 15 at 7 AM. Estimated completion:May 14.

Ross County Guardrail Replacement – Various county roads will be reduced to one lane daily from 7 AM to 5 PM starting March 1. Traffic will be maintained using flaggers.Estimated completion: Summer 2021

U.S. 23 Slide Repair – U.S. 23 northbound will experience intermittent single-lane closures south of S.R. 372. Restrictions will be set up as needed for construction. When in effect, restrictions will occur between 7 AM and 5 PM. Estimated completion: Spring 2021

The following construction projects are anticipated to affect highways in Pike County next week. All outlined work is weather permitting.

NEW* Pike S.R. 32 Resurfacing – S.R. 32 will be reduced to one lane in each direction between Goff Road and S.R. 124 starting May 10 at 7 AM. Estimated completion: Fall 2021

NEW* Pike S.R. 335 Resurfacing – S.R. 335 will be reduced to one lane daily from 7 AM – 5 PM, Mon-Fri between Simmons Hollow Road and the village of Waverly beginning May 10. Traffic will be maintained using flaggers. Estimated completion: Summer 2021

U.S. 23 Signal Upgrade – U.S. 23 will be reduced to one lane in each direction daily from 7 AM to 5 PM on either side of the intersection with Second Street immediately south of the village of Waverly beginning March 24. Estimated completion: Summer 2021

S.R. 772 Slide Repair – S.R. 772 will be reduced to one, 13-foot lane between S.R. 124 and McKinney Road starting March 15 at 7 AM. Traffic will be maintained using temporary signals. Estimated completion: Summer 2021

Pike Lake State Park Resurfacing – Various park roads in Pike Lake State Park will be reduced to one lane daily from 7 AM – 5 PM starting March 15. Traffic will be maintained using flaggers. Estimated completion: Spring 2021

S.R. 32/Shyville Road Intersection Improvement – Beginning March 15, traffic lanes on S.R. 32 will be shifted in advance of construction of a new RCUT intersection design. S.R. 32 is reduced to one lane in each direction immediately east and west of the Shyville Road intersection. Estimated completion: Summer 2021

The following construction projects are anticipated to affect highways in Highland County next week. All outlined work is weather permitting.

S.R. 28/S.R. 138/S.R. 753 Resurfacing – This project will resurface portions of three routes in Highland County starting April 19: S.R. 28 between Leesburg and Greenfield; S.R. 138 between 7th Street and Jefferson Street in the village of Greenfield; S.R. 753 between Snake Road and McKell Avenue. The affected routes will be reduced to one lane daily from 7 AM to 5 PM during construction. Traffic will be maintained using flaggers.Estimated completion: Summer 2021

U.S. 62 Resurfacing – U.S. 62 will be reduced to one lane between the village of Hillsboro and Warlamount Road daily from 7 AM to 5 PM starting March 29. Traffic will be maintained using temporary signals. Estimated completion: Summer 2021

The following construction projects are anticipated to affect highways in Scioto County next week. All outlined work is weather permitting.

U.S. 52 Culvert replacements – This project will replace two culverts along U.S. 52 starting April 1. The first culvert is located east of Upper Twin Creek Road. The second culvert is located between Pond Run Road and Ziegler Lane. Construction for both culverts will occur simultaneously. For both locations, traffic on U.S. 52 will be maintained in one lane using temporary signals. Estimated completion: Summer 2021

Riverfront Multi-Use Path – This project will construct a multi-use path between Front Street and Offnere Street beginning April 1. Traffic on affected city streets and school roads will be maintained in one lane using flaggers as needed. Restrictions may occur daily between 7:30 AM and 5 PM. Estimated completion: Fall 2021

U.S. 23/Feurt Hill Road Intersection Improvement – Feurt Hill Road may be reduced to one lane as needed during construction, with traffic maintained using flaggers. Two lanes in each direction will be maintained on U.S. 23 throughout construction. Estimated completion: Fall 2021

State Route 823 routine maintenance – state Route 823 will be reduced to one, 14-foot lane in each direction daily from 6:30 a.m. to 6:30 p.m. for routine maintenance, pavement grinding, and other work as needed from May 12 to May 13. Estimated completion: May 13, by 6:30 p.m.

The following construction and maintenance projects are anticipated to affect highways in Adams County next week. All outlined work is weather permitting.

NEW* S.R. 136 Culvert Replacement – S.R. 136 will be closed between Berry Road and Wildcat Road starting at 7:30 AM on May 4. Traffic will be detoured via S.R. 32 and U.S. 62. Estimated completion: May 4 by 3:30 PM

S.R. 32 Culvert Replacement – S.R. 32 will be reduced to one, 10-foot lane in each direction between Pine Hollow Road and Black Hollow Road starting April 26. Estimated completion: Summer 2021

S.R. 32 Resurfacing – S.R. 32 will be reduced to one lane in each direction between Tranquility Pike and S.R. 73 starting April 5. Estimated completion: Fall 2021

District-wide Reflective Pavement Marker Installation – Currently working in Adams County. Beginning March 22, work will commence on various routes throughout the district from 7 AM to 5 PM daily. Traffic on two lane roadways will be maintained in one lane using flaggers. Traffic on four lane roadways will be maintained in at least one lane in each direction during work hours. Estimated completion: Summer 2021

The following construction projects are anticipated to affect highways in Brown County next week. All outlined work is weather permitting.

NEW* S.R. 125 Resurfacing – S.R. 125 will be reduced to one lane daily from 7 AM to 5 PM between Gillette Station Road and the Clermont County Line starting May 3. Traffic will be maintained using flaggers. Estimated completion: Fall 2021

State Route 125 bridge replacement at Georgetown – S.R. 125 may be restricted to one lane to complete construction on the White Oak Creek bridge replacement project, with traffic maintained using flaggers as needed. Restrictions, when needed, will be in effect daily from 7 AM to 5 PM. Estimated completion: Spring 2021

U.S. 52 Culvert Replacement – U.S. 52 will be reduced to one lane between Elk River Road and Logan Gap Road starting April 12 at 7 AM. Traffic will be maintained using temporary signals. Estimated completion: Summer 2021

S.R. 41 Slide Repair – S.R. 41 will be reduced to one lane between Meffords Run Road and Catbird Lane starting at 7 AM on April 19. Traffic will be maintained using temporary signals. Estimated completion: Summer 2021

Village of Aberdeen Sidewalk Upgrades – This project will install new pedestrian facilities in the village of Aberdeen at the intersection of U.S. 52 and Elm Street starting March 29. Traffic on U.S. 52 will be maintained in one lane in each direction throughout construction, with minor traffic impacts possible. Estimated completion: Summer 2021

The following construction and maintenance projects are anticipated to affect highways in Lawrence County next week. All outlined work is weather permitting.

NEW* S.R. 775 Double Bridge Replacement – S.R. 775 will be reduced to one lane north and south of Venisonham-Camp Branch Road beginning May 17. The road will be closed for this construction. Traffic on C.R. 64 (Venisonham-Camp Branch Road) will be maintained in one lane using temporary signals for construction of the bridge immediately south of the intersection. During periods of closure, traffic will be detoured via S.R. 141, S.R. 378, and S.R. 217. Estimated completion: Fall 2021

NEW* S.R. 217 Slide Repair – S.R. 217 will be closed for five days beginning May 3 approximately 1.5 miles east of Big Paddy Road. Traffic will be detoured via S.R. 218, S.R. 553, and S.R. 7. Estimated completion: May 7 by 5 PM

S.R. 217 Slide Repair – S.R. 217 will be closed for five days beginning April 26 approximately one mile east of Big Paddy Road. Traffic will be detoured via S.R. 218, S.R. 553, and S.R. 7. Estimated completion: April 30 by 5 PM

S.R. 243/S.R. 378 Resurfacing – This project will resurface segments of both S.R. 243 and S.R. 378, as well as replace a culvert on S.R. 378. Traffic on the affected routes will be reduced to one lane daily from 7 AM to 5 PM beginning April 1. Traffic will be maintained using flaggers. Estimated completion: Fall 2021

U.S. 52 Bridge Repair and Maintenance – This project will perform various maintenance and repair work to several bridges along U.S. 52 starting April 1. Traffic will be maintained in one, 10-foot lane in each direction of U.S. 52 throughout construction. This project will include two, 14-day ramp closures at the U.S. 52/S.R. 93 interchange. During the ramp closures, traffic will be detoured via U.S. 52 and S.R. 141. Estimated completion: Fall 2021

State Route 7 Rockslide Remediation – S.R. 7 southbound between Buffalo Creek Road and Tallow Ridge Road is reduced to one, 12-foot lane. Additional traffic control measures may be necessary as construction progresses. Estimated completion: Spring 2021

Pickaway County Road Reports

U.S. Route 62

CONTINUING IMPACTS
U.S. Route 62 Bridge Replacement – The U.S. 62 bridge over Deer Creek will close starting Monday, March 15 through September 2021 for bridge replacement. Detour: U.S. 62 to I-71 to SR 56 to U.S. 62 or reverse.

Vinton County Road Reports

SR 683 culvert replacement – A culvert replacement project begins on May 3 on SR 683, between Zion Road (County Road 37) and Township Road 27. The road will be closed. ODOT’s detour is SR 93 to U.S. 50. Estimated completion: May 4, 2021

Wild Turkey Festival – U.S. 50 will be closed in the Village of McArthur for the Wild Turkey Festival, being held from May 5-9.